Thank you for using ROB-EX Scheduler, the best tool for manual and automatic visual production scheduling. This manual describes functionality and usage of ROB-EX Scheduler Planner and ROB-EX Scheduler Viewer for version 6.4. If you are new to ROB-EX Scheduler, then…

REST Server

Import and export » REST Server

Page Content Introduction Requirements Starting the REST server Test connection FAQ / Troubleshooting Introduction When enabled, the REST Server, provides the user with a REST Based Client API (a set of web-services). This allows for custom integration…

Product configuration

Product configuration

Welcome to the documentation for users/consultants performing additional configuration or development on ROB-EX clients. The documentation includes chapters on Installation FAQ (Frequently Asked Questions) Changing global parameters affecting GUI and business logic…

Scheduling

Scheduling

Scheduling orders : How to schedule or reschedule orders in ROB-EX. Scheduling strategy window: Strategies and setting available when planning in ROB-EX. Setting a default scheduling strategy : How to set the default scheduling strategy used for new…

View menu

The user interface » Gantt chart » Menu » View menu

Click on… if you want to… Order name View order name together with the orders The order name is viewed above the order in the Gantt window. The order name is shown as a text above each operation in the Gantt plan. The…

Functions menu

The user interface » Gantt chart » Menu » Functions menu

The menu Functions contains the following options: General Settings Scheduling Strategy XML Plugin Database Plugin Textfile Plugin Manpower User management Macro->Edit Script console Settings – Scheduling strategy Select a scheduling…

Interfacing using Talend Open Studio for Data Integration

Import and export » Interfacing using Talend Open Studio for Data Integration

An easy and recommended approach, when building interfaces between ROB-EX and external systems like ERP, is to use an ETL tool (Exctract, Transform, Load). Using a tool reduces the learning curve required, enabling non-developers to create even complex…

SplitOperationsByStorageSpace

Macro » SplitOperationsByStorageSpace

Split or move producing operations to suitable warehouse resources – where there are enough space. If a warehouse is found with enough space for the entire operation it is moved to the resource assigned to that warehouse. Otherwise the operation is splitted and…

SelectComponents

Macro » SelectComponents

This will select operations based on the specified parameter settings. The parameters can be combined i.e. both resource and status can be used etc. As an example select all operations on a given resource having order state Started. You would typically use the…

UpdatePlan

Macro » UpdatePlan

This macro will move orders forward that did not start up on time and repair invalid areas of the schedule. The current sequence of the jobs on the resources will if possible be kept, but it cannot be guaranteed. Operations with status complete or being locked will…

CheckShelfLife

Macro » CheckShelfLife

Check if shelf life is exceeded. This macro will show a list of operations consuming a material which is too old. Pegging must be done first in order to check for shelf life (shelflife). Suborder links are also supported. Example parameter configuration …

Resource Monitor Quick Guide

Reporting and KPI » Resource monitor » Resource Monitor Quick Guide

Once connected to the App, start out selecting the resources you would like to display. They are shown on the page in the sequence they are selected Select if you would like to display the resource KPI’s in Hours or in Quantity. Note, that if Quantity is…

The Progress tab

Master data » Master routes » Operation list » Editing operation details » The Progress tab

The progress function can get its information (partial completions) by Manually entering the information in this window. A typical way to get to the tab, is by double clicking an operation in the Gantt chart. The window Edit operation is opened. For Started…

Schedule

Macro » Schedule

This will re-schedule the selected production orders in the sequence they are currently selected. Starting from ROB-EX Scheduler 7.2.4, this macro will utilize the Selection context feature. For a more flexible alternative also see the SortAndSchedule macro command. …

.NET Client

Import and export » REST Server » .NET Client

Page Content Introduction Requirements .NET API documentation Simple use cases Advanced use cases Introduction To give the users the ability to easily create a .NET Client that integrates with ROB-EX, we have implemented the .NET Assembly deployed in…

Activating a license

Getting Started » Starting up the client » Licensing version 6.4 and newer » Activating a license

The first time you start a ROB-EX Desktop Planner, a wizard will pop up, asking you to register and activate your license. The first step is to select a license type. The Floating license is the recommended and default way to deploy ROB-EX Scheduler in a multiuser…

Developing using the API

Product configuration » Developing using the API

API Developers Kit The API Developers Kit will enable custom programs to be written and executed embedded into the ROB-EX client. The program or script written interacts with the ROB-EX client through a Java based API (Application Programming Interface). The API will…

Time Tracker

Options » Time Tracker

ROB-EX Time Tracker is an App optimized for mobile devices allowing named operators to check in and check out at the operation level. When doing a check-out or partial completion, the client automatically suggests logging past hours since the previous check-in. In…

Licensing of versions prior to 6.4

Getting Started » Starting up the client » Licensing of versions prior to 6.4

The following applies to ROB-EX version 6.2 and older versions. For version 6.4 and newer read instead Licensing version 6.4 and newer. The first time you start ROB-EX Scheduler you will be asked to register. Press the register button. You are presented with a unique…

Tab: Shop Floor

Advanced functions » General settings » Tab: Shop Floor

Also visit the general introduction to ROB-EX Shopfloor. If the Shopfloor web-server should be automatically started when the ROB-EX client is started. The web-server must be running before any user can log into the Shopfloor pages. However setting up…

Archiving

Options » Multiuser » Archiving

The archive functions in ROB-EX is used to remove data from ROB-EX Scheduler Client no longer needed for the planning process, but still retain the data in the ROB-EX Scheduler database. This is typically old data which cannot be deleted for different reasons. As an…

MakePlace

Macro » MakePlace

Any operation overlapping one or more of the currently selected operations are moved forward in time until no more overlap exists. Example parameter configuration Parameter descriptions (* = configuration required) statusListUntouchable A comma separated…

Creating resources

Getting Started » Solving my first scheduling problem » Creating resources

Start out creating all the resources you are going to plan for. In the menu select “Edit/Resource”. The following dialog Edit resource will be shown. Right click on the headline Resources in the top right corner of the resource list and select…

Resource Monitor System configuration

Reporting and KPI » Resource monitor » Resource Monitor System configuration

This is a quick guide for the ROB-EX system administrator, explaining how to configure the web-server side of the ROB-EX Resource Monitor App. If not already running, configure ROB-EX Integration client to run as a service. Make sure the integration client starts…

REST Client

Import and export » REST Server » REST Client

Page Content Introduction REST Client API Documentation Requirements Simple use cases Advanced use cases FAQ / Troubleshooting Introduction With the REST Server started, the user can create a custom integration, using any programming language they desire,…

Operation split and join

Production orders » Operation split and join

Use the Split operation function to split operations into two or more operations. The function is available by double clicking in the column “Split” in the operations list of the route editor selecting “Split operation” in the shortcut menu,…

Status overview

Product configuration » Misc and background » Status overview

Order status overview Table of supported order states Status text Status level Incomplete 5 New 10 Forecast 15 Planned 20 Released 30 Start…

CreateProductionOrder

Macro » CreateProductionOrder

Will create a new production order. Example parameter configuration Parameter descriptions (* = configuration required) allowMoveInResourceGroup false = Move within resourcegroup allowed. createAsPlanned false = Status will be set to new true = Status will…

AdjustResource

Macro » AdjustResource

The selected operation will be moved to the specified date and the rest of the operations within the specified period will be replanned. Specify the date by using the dialog shown below. Example parameter configuration The three horizons can be specified in…

Attached documents

Master data » Attached documents

External documents, such as Word documents, spreadsheets, drawings, links to homepages etc. can be attached to e.g. operations or orders in ROB-EX. The “Documents” dialog (go to “Edit -> Documents”) shows a list of all the documents which are…

Startup caching

Getting Started » Starting up the client » Startup caching

From ROB-EX Scheduler v6.4.1.814 we provide new versions of \bin\ROB-EX Gantt.exe and \bin\ROB-EX Viewer.exe which will automatically cache data on the user’s local pc during startup. This decreases the startup speed, but most importantly also fixes issues with…

Tool bar

The user interface » Gantt chart » Tool bar

Click on… if you want to… New Create a new plan. The present plan is cleared for orders but the selected resources are preserved. It is advisable to save the former plan with the functions Save or Save as…

Searching, sorting and filtering using the Order list

Production orders » Order list window » Searching, sorting and filtering using the Order list

The Order list contains many features for searching, sorting and filtering out production orders. Configuring displayed columns Make sure you have added all the important columns you need to the order list. The table is 100% configurable when it comes to adding and…

SetOperationStatus

Macro » SetOperationStatus

Changes the status to the specified value for all operations currently selected in the gantt chart. Example parameter configuration Parameter descriptions (* = configuration required) force force a status change even though it may not correspond to the…

Changing the UI language

Product configuration » Changing the UI language

Runtime language configuration Introduction This is a description of how to customize the text shown in ROB-EX in the various dialogs and menus. All the text in ROB-EX is stored in so called language files. The default language is English and the English texts are…

Alternate routes

Master data » Master routes » Alternate routes

As an example of how to get started using alternate routes these step-by-step instructions shows how to configure a simple plan to use alternate routes. The example shown below is available in the planning file “\data\alternate route example.xml”…

The graph area

The user interface » Gantt chart » The graph area

The graph area shows different kinds of graphs, such as Workload graph Manpower graph (refer to chapter Optional modules->Manpower) Material graph (refer to chapter Optional modules->BOM) If more graphs are selected to be shown at the same time, a scroll bar is…

RunExternalProgram

Macro » RunExternalProgram

This will start a specified program and pass on the values from the specified variables. Starting from ROB-EX Scheduler 7.2.4, this macro will utilize the Selection context feature. List of available variables: Variable list. Example parameter configuration …

Controlled overlap

Master data » Master routes » Operation list » Editing operation details » The Times tab » Controlled overlap

The function controlled overlap supports different kinds of overlap (send-ahead) between two operations. The function is available when double-clicking on an operation in the Gantt chart and the window Edit operation will show up, on the Times tab the settings for…

Using the ROB-EX installer

Getting Started » Installing the client » Using the ROB-EX installer

The same ROB-EX installer is able to install all the different components of ROB-EX Planner and Viewer Desktop Client Integration Client Floating License Server The ROB-EX installer is started up multiple times – each time selecting what component to…

Sub-operations

Master data » Master routes » Operation list » Sub-operations

Table of contents Introduction Using sub-operations Creating sub-operations Editing sub-operations Adding sub-operations to normal operations Scheduling with sub-operations Introduction A sub-operation is a special type of operation that can be…

Detail panel

The user interface » Gantt chart » Detail panel

Mark an operation in the Gantt chart and see detailed information about the selected operation, order, and project The panel is activated/deactivated in the menu View. Operation Production order Project (Only with ROB-EX Project) Manpower (Only with ROB-EX…

Integration client

Advanced functions » Integration client

The ROB-EX Scheduler client can as needed be installed to run as a Windows service. This is typically useful when a ROB-EX Scheduler client needs to run unattended batch jobs like interfacing to external ERP systems, running the Shop Floor server, automatic generation…

Proficy Workflow Client

Import and export » REST Server » Proficy Workflow Client

Page Content Introduction Requirements Installation Usage Example FAQ / Troubleshooting Introduction ROB-EX and Proficy Workflow can be easily integrated by using the Service Provider implementation implemented in the Robex.Workflow.dll. For documentation on…

Variable list of columns

Product configuration » Variable list of columns

Below is a list of possible variables to access column/field values from operation, production order, project etc. These are the same variables used, when you add columns through the field chooser in ROB-EX and presented in a table. As an example the order list. *If…

Direct SQL Integration

Import and export » Direct SQL Integration

The principle behind this integration is that on a push of a button in the ROB-EX client, SQL calls are executed on the ROB-EX client towards the database of the ERP system. The SQL itself can be modified from application to application, but ready made templates are…

GenerateReport

Macro » GenerateReport

This macro can silently (option) generate both HTML reports (i.e. menu File->Print HTML) as well as prints of the current resource or project gantt view (i.e. menu File->Print). Example parameters for printing HTML report Example parameters for printing…

Interfacing with Operation split and join

Import and export » Interfacing with Operation split and join

This chapter describes how to handle interfacing when performing split and join in ROB-EX at operation level (split at order level is another subject). The challenge is how interface wise, to handle the additional Operation objects created after a split. To further…

Tab: Standard

Advanced functions » General settings » Tab: Standard

Standard settings for Orders Default values and settings for orders If checked, this will set the precondition flag when creating new orders. The default priority or new orders. The default customer for new…

Tab: Progress

Advanced functions » General settings » Tab: Progress

Progress settings concerns functionality in ROB-EX concerning the progress in hours, quantity or % on a started operation. The concepts are: Completely turn off use of progress information in ROB-EX (both presentation and import/export) …

ExtractReportingHistory

Macro » ExtractReportingHistory

This will calculate resource load data and save it to the GanttMultiuser database in table EReportingHistory. Notice that the client has to be logged in to the multiuser! As an alternative see WorkloadOverviewExportII Example parameter configuration Parameter…

Starting the app

Reporting and KPI » Dashboard App » Starting the app

Get the HTTP address of the ROB-EX Integration Client. Contact your ROB-EX system administrator. It will look like this: http://robexsrv01:9999 On your mobile or desktop device open a modern web-browser (e.g. Chrome, Edge, Safari) Enter and Bookmark the URL for the…

Starting the App

Reporting and KPI » Resource monitor » Starting the App

Get the HTTP URL of the ROB-EX Integration Client. Contact your ROB-EX system administrator. It will look like this: http://robexsrv01 On your mobile or desktop device open a web-browser (e.g. Chrome, Edge, Safari) Enter and Bookmark the URL for the Resource…

SplitOrderToBatches

Macro » SplitOrderToBatches

This macro makes it possible to split orders into batches. The macro will split orders according to configuration parameters found on the objects in ROB-EX. The macro will split all orders belonging to the selected operations. OBS: ALL SPLITS ARE FINAL. Parameter…

GanttSetup.properties file

Product configuration » Global client settings » GanttSetup.properties file

# ROB-EX property file # Copyright (c) 2011 NOVOTEK PLANNING SYSTEMS Misc # Location of Gantt log file. If not specified it will be placed in # users documents and settings area # logfile.location=C\:\\temp\\robexlog # Dateformat used for loading/saving of…

Installing the client

Getting Started » Installing the client

This document explains the steps necessary to install a new ROB-EX Scheduler client. Installation of the ROB-EX Scheduler Multiuser Server is optional and is a separate topic you can read more about in the Multiuser server section. Preparation First make sure that…

Command line options

Getting Started » Starting up the client » Command line options

Different options can be passed to the ROB-EX Gantt.exe file to further control the different features of the product. By specifying -help or /? on the command line the different possible options will be displayed. The options are passed to the .exe file by right…

Server installation

Options » Multiuser » Server installation

Installation and Administration guide Table of contents Preparation Installation of ROB-EX Multiuser Server Updating an existing ROB-EX Multiuser Server Starting up ROB-EX Multiuser Server and Clients Stopping ROB-EX Multiuser Server 64-bit NT Service Connect…

Sequencer

Options » Sequencer

Introduction and overview Quick Start guide Setup and configuration of Sequencer Defining value profiles Syntax for defining a ValueProfile Syntax for defining a ValueProvider Lookup table value…

Time and Attendance import

Import and export » Time and Attendance import

This optional module is capable of importing progress registrations from an external data collection system and assign the progress information to correct operation in ROB-EX Scheduler. Note: requires license to “CSV Progress” import module (see…

Macro

Macro

General overview List of available macro command lines General overview The Macro list window (“Functions->Macro->Edit”) enables you to create macros to automate frequently performed tasks. A macro has a name and an associated icon that can be made…

UpdateOrderDates

Macro » UpdateOrderDates

This will update the material and delivery date fields on the selected production orders. The update will be performed according to the operations in the order. For instance the delivery calendar will be set to the latest operation’s end calendar and the material…

Shop Floor

Options » Shop Floor

ROB-EX Shop Floor allows the user to view the current production schedule using a standard internet browser. Table of contents Introduction Edit group Edit user Start the web server Log on the web server Setup appearance The job list Order details Operation…

Materials and BOM

Master data » Materials and BOM

Bill of material The ROB-EX Scheduler Bill of Material (BOM) module supports simultaneous scheduling of both capacity and material. This module supports the creation of master materials and the creation of stock transactions like counting’s, purchases and…

Using relative file paths with Talend

Import and export » Interfacing using Talend Open Studio for Data Integration » Using relative file paths with Talend

Very often with Talend, it makes good sense to export and import files using a file-path being relative to the ROB-EX client folder. I.e. if your ROB-EX client folder in production is a network drive like \\myserver\robex\planner and you import and export from…

AdjustOrderQuantityToInventory

Macro » AdjustOrderQuantityToInventory

Adjust operation or order quantity based on the stock level for the material consumed by the selected operation. If there’s a positive stock level after the operation end time and a specified horizon ahead. Adjust the qty up so all material is consumed and thus…

XML

Import and export » XML

This chapter will explain how to interface between an external system (e.g. ERP) and ROB-EX using the XML integration module. It is possible to transfer data both ways. Data possible to transfer with XML interface Resources Resource calendar Products and raw…

JoinOrders

Macro » JoinOrders

This macro can join multiple selected orders into one – if they use the same route. Select one operation in each order to join. The first selected order will be retained and the others will get deleted. The quantity sum is set on the retained order. All links…

UpdateMaterialDates

Macro » UpdateMaterialDates

This will find the earliest possible start (materials ready) for the selected operations. The material date on the orders are updated and the operations can be moved to the material date automatically. Example parameter configuration Preconditions BOM must be…

Special routing cases

Scheduling » Special routing cases

Scheduling with disabled operations Special considerations should be taken when scheduling production orders containing disabled operations. Please read more about this in the routing description section. Scheduling with locked operations Locked operations are not…

Master routes

Master data » Master routes

This chapter explains how to edit existing routes or create new routes. Please refer to the chapter Getting started – Creating master routes” for a full example on how-to create new master routes. Changes to master routes made from…

Shop Floor configuration

Options » Shop Floor » Shop Floor configuration

Introduction This document describes how to configure the appearance and behavior of the Shop Floor interface. Examples of how to add/remove columns, change the names and widths of the columns are illustrated. Then some more specific features are described i.e.…

ProjectDBSync

Macro » ProjectDBSync

This will perform a project DB synchronization. This macro element has no user parameters. Note: This function is only avaible with SQL XAL Project integration module. Example parameter configuration To setup the DB connection and other general DB settings, go…

License deactivation

Getting Started » Starting up the client » Licensing version 6.4 and newer » License deactivation

An activated license stays activated until any of these events occurs The license is manually deactivated by the user. The tamper-prevention mechanism of our license technology, detect the machine the license was activated on, has changed significantly. Manually…

SortAndSchedule

Macro » SortAndSchedule

This macro command supports easy rescheduling of orders based on one or more configurable sorting fields. Starting from ROB-EX Scheduler 7.2.4, this macro will utilize the Selection context feature. In more detail the SortAndSchedule macro command will carry out the…

Templates

Advanced functions » Templates

With this dialog you can perform maintenance of your templates. There are 3 kinds of templates Macros (automation of often performed tasks) Table properties (e.g. what table columns to show) and View layouts (what text to show about Gantt bars). Templates in use…

XML minimal example

Import and export » XML » XML minimal example

This is the “Hello world” example for ROB-EX XML import, showing the minimum required information that must be supplied in order to import 2 resources and 1 production order with 2 operations into ROB-EX. Essentials of the XML document structure is…

Order list window

Production orders » Order list window

The Order List window provides an overview of all production orders contained in the ROB-EX client. You get to this window by either selecting menu Edit->Order list or by clicking the order list icon in the tool bar. You may also jump to this window from other…

Full Multiuser Deployment example

Getting Started » Installing the client » Full Multiuser Deployment example

Introduction This single server deployment architecture is used in multiuser setups for small to medium sized ROB-EX Scheduler deployments with typically 1-5 simultaneous planners all working out of the same physical location. 1-10 simultaneous viewers 1-2 sites…

Tab: Multiuser

Advanced functions » General settings » Tab: Multiuser

This tab controls the Multiuser login information enabling a ROB-EX client to connect to a ROB-EX Multiuser Server. The tab also controls setup, execution and information about archiving. The Archive area in this tab is only enabled for users logged in to the…

SetOprCalendar

Macro » SetOprCalendar

Will set the start or end calendar on one or more currently selected operations. A calendar chooser is shown to the user allowing him to enter/select the new date and time (only shown if no “autoSetCalendarRule” has been specified) Example parameter…

The Attached Documents tab

Master data » Master routes » Operation list » Editing operation details » The Attached Documents tab

External documents, such as Word documents, spreadsheets, drawing, links to homepages etc. can be attached to operations in ROB-EX. Select “External documents” in the shortcut menu (Right click on an operation). A list of documents attached to the operation…

Attached documents

Master data » Resources » Resource tree » Attached documents

External documents, such as Word documents, spreadsheets, drawings, links to homepages etc. can be attached to resources in ROB-EX. Select External documents in the shortcut menu (Right-click on an operation). A list of documents attached to the operation is shown.…

Solving my first scheduling problem

Getting Started » Solving my first scheduling problem

This chapter demonstrates key features of the ROB-EX Scheduler client with the purpose of providing new users with an understanding of How to define and scope the scheduling problem How to model the scheduling problem inside ROB-EX Scheduler How to solve the…

Selecting the runtime language

Getting Started » Starting up the client » Selecting the runtime language

This setting controls text on labels, menus, buttons, etc. Add the locale parameter as shown below. In the example the parameters “en IE” (case matters !!!) added to the Target line will start a client with English (en) language using Irish (IE) regional…

Multiuser

Options » Multiuser

ROB-EX Multiuser enables multiple users to work in the same plan at the same time, i.e. a change made on Client1 is immediately available and visible on Client2. Each user is assigned a login, a role and the permission to connect to one or more sites. The role of a…

Interface History Manager

Import and export » Interface History Manager

The interface history manager is used on integration clients to inform other ROB-EX Scheduler clients about the current status of the interface between ROB-EX and an external ERP system. In combination with the integration status bar, other clients will be able to…

ResetSplit

Macro » ResetSplit

This macro command can join operations which are split. Furthermore it can delete suborder links, delete linked CIP orders and move original operations back to their resource groups. Select one of the split operations and it will find all the other split members in…

Tab: Integration

Advanced functions » General settings » Tab: Integration

This tab affects the behaviour concerning integration to ERP systems using any of the modules: XML integration During import of operations ROB-EX will automatically create a template operation for each new operation name imported. If this option is…

The Times tab

Master data » Master routes » Operation list » Editing operation details » The Times tab

Field Explanation Quantity factor Adjust the number of pieces on the specific operation. Example: An order produces 100 tables. The current operation produces table legs. For every table on the production order, this operation produces 4…

SQL integration

Import and export » SQL integration

This chapter describes the integration between an ERP system and ROB-EX using an integration database. Data are exchanged between ROB-EX and the ERP system through a neutral integration database named ‘GanttERP2’. Data possible to transfer with the…

Creating master operations

Getting Started » Solving my first scheduling problem » Creating master operations

Once shift calendars and resources has been defined, it is time to create the master operations which are needed in order to create routes. An operation in the ROB-EX Scheduler term, describes a process to perform (i.e. cut, grind, etc.) and the list of resources…

Pegging

Macro » Pegging

This macro will create pegging links (material dependencies) between operations which respectively consume and produce a semi finished product. A good understanding of the ROB-EX BOM module is vital to understand the concepts of the pegging macro. Background A…

CSV 1 integration

Import and export » CSV integration » CSV 1 integration

This chapter describes the setup and use of the module CSV 1 integration for ROB-EX Scheduler. Using this module text files with data delimited by comma, semi colon etc. containing order and routing information can be imported into ROB-EX. The following are examples…

TextSingleLineExport

Macro » TextSingleLineExport

Will export order information to a text file. Each row in the generated text file contains information about a single operation in ROB-EX Scheduler, including the project and production order it belongs to. Operations are grouped by production order and the sequence of…

The Advanced tab

Master data » Master routes » Operation list » Editing operation details » The Advanced tab

The advanced tab allows control of less commonly used advanced options. Calendar settings Respect resource calendar If “Yes” is selected (the default) the duration of the operation will be calculated with respect to open and closed periods. If…

Transition rules

Scheduling » Scheduling Settings on Resources » Transition rules

Resource Transition Rules will add more detailed constraint modeling, down to single-resource and single-product. The transition rules enable the possibility to block resource changes depending on the previous or next operations (i.e. not only based on the current…

Right click menu

The user interface » Gantt chart » Right click menu

Functions for adjusting operations and orders in the Gantt chart. Use the right mouse button to click on an operation in the plan. Selecting Select order Select all activities in the order. The function is used when all activities in an order is to be moved in…

Editing operation details

Master data » Master routes » Operation list » Editing operation details

You may edit an operation by: double clicking on an operation in the route list (in e.g. the the Edit->Route window or from the Order list). double clicking on an operation in the Gantt chart selecting Edit operation in the right-click short cut menu The…

Creating a general calendar

Master data » Shift calendars » Creating a general calendar